Thai-Chinese Railway Project: Section 4-3 Construction Delayed Due to Flood Damage, Completion Extended
Infrastructure

Thai-Chinese Railway Project: Section 4-3 Construction Delayed Due to Flood Damage, Completion Extended

The State Railway of Thailand (SRT) board has approved a 239-day extension for the completion of Section 4-3 (Nawana Khong - Ban Pho) of the Thai-Chinese railway project, pushing the deadline to July 26, 2027, primarily due to flood damage in Ayutthaya.